
The main works carried out in the river were the introduction of:
-
-
-
-
Work proceeded from downstream to upstream to take account of any water level changes and interactions between the various measures.
The placing of the stone and gravel in the river to form the riffles, and the setting
of the LWD, were the most intensive parts of the works. These required the use of
a tracked digger and a 3.5t dumper truck, with our consultant Vaughan Lewis directing
the operations and driving the dumper. This work was carried out on the 5th October,
and on the 11th and 12th October; but with subsequent much hand labour to form the
upper cattle crossing/riffle, and re-
Vaughan was also with us on the 3rd and 4th October. The work carried out then was the bank narrowing and island creation work, working with hazel materials. This used no heavy machinery but was labour intensive.
Running parallel to the in-
SUMMARY OF WORK UNDERTAKEN