
Reject flint from Cemex stacked at the hard surface area was loaded by a digger into
a 3t dumper which ferried it to the various areas of river bank where it was to be
used, and similarly for the gravel. The stone was placed by digger in the river
bed to a depth to around 75% of the final level of stone and gravel required. The
lengths of the riffles were a compromise between the ideal (15 metres or more) and
what could be contained within the project costs, and the material spread by the
digger bucket. The stone was followed by the upper layer of 20-
The first and last (sixth) riffles were formed to serve as both a riffle and a cattle crossing. The other four riffles were set so as leave a narrow and deep run along the side of the far bank for the benefit of larger trout. Best estimates of the amounts of stone in gravel in each are shown below.
Length Reject Flint Gravel Total
CC1/Riffle 1. 8m 17t 5t 22t
Riffle 2. 13m 24t 7t 31t
Riffle 3. 15m 27t 8t 35t
Riffle 4. 10m 18t 9t 27t
Riffle 5. 12m 21t 10t 31t
CC3/Riffle 6. 4m 8t 1t 9t
Total. 62m 115t 40t 155t
The deeper the river section, the more reject flint required. The positions of the riffles are shown on map 2, which shows the location for all the finished works.
The licence plan submitted to the Environment Agency was for up to 10 small riffles
(including the two with dual function as cattle crossings/drinks) from the screened
gravel, with a length of riffle at 15m or more in length. The riffle would increase
the retained head by 15-
There is an option over time to extend the length of the riffles by hand labour should more stone and gravel material become available and experience indicated this would be beneficial. In fact, cattle crossing 3 was done by hand, after the other riffles were done by heavy plant work. Some local sourced reject flint was barrowed in, and all the gravel gleaned by rake and shovel from the digger spill on the bank side of the other riffles.
The need to build a bridge over the side channel at cattle crossing 2 required that the stone that had been placed there was supplemented by spoil to give a firm base on which to place the sleepers. The stream here was about a metre wide with a bed of small stone and gravel bed in shallow water. After the bridge was removed, the digger then cleared the stream, and levelled the stone and spoil over the approaches. This was followed by 4 days of digging by hand to recover the large stone that had been placed there and the material that had formed the channel bed. With some additional replenishment the bed of the stream was enhanced and extended on completion of this work, with a length of small stone and gravel extended from
2.75 m to 9 m.
RIFFLES







For larger photographs of the thumbnails on this page together with a brief description and [day/month]
