
This is a companion report to that on the river restoration project carried out on a stretch of the River Glaven upstream of Letheringsett Ford. This was the first practical river restoration project to be carried out by the River Glaven Conservation Group (RGCG), a voluntary body with a local membership. The project involved several different types of remedial measures, not all of which are as yet commonly done. Based on this experience, we set out a number of factors that were important to take into account when planning and implementing the programme of works.
This section is intended for others embarking on a similar chalkstream project.
TIME OF YEAR
Ideally the in-
TERRAIN AND LOGISTICS
One advantage of the site we selected was the use of local knowledge to ascertain how materials might be brought in and deployed to where they will be needed on site, in particular where heavy plant is to be used. Also in our case how heavy material (spoil) may be taken off site and where it can be disposed. For delivery of materials and other contacts it is a useful bonus if a team member lives close to the site.
THE LICENCE OF CONSENT
No work can start on the river itself until the application for consent is approved
by the Environment Agency. Given the complexity of our programme and other special
reasons our six week clearance time was unusually fast. It may be necessary to think
in months rather than weeks. The preparation of the document itself for the Agency
requires some specialist skills and time. Prior to this a pre-
OVERALL TIMESCALES
Build in the necessary time for obtaining the licence of consent and other necessary
steps required before practical work can start, and then work backwards from August-
PREPARATION WORK
Note that application processing time can be well spent on careful planning of the
work, and taking this through to some preparation as regards the provision of materials
to be used. The latter applies in particular to tree and woody materials as a source
of large woody debris deflectors and coppiced hazel for the faggots, stakes, batons,
pegs and brash that will be required. It is important to carry out studies on any
protected species that might otherwise suffer inadvertently from the proposed works,
such as water vole, otter and white-
SPECIALIST HELP
The RGCG had the benefit of a specialist advisory visit in thinking through the concept in principle of “what might be done where” on the stretch of river selected. Given our (lack of) experience, and the unavoidably tight timescale, it was essential to enlist the aide of a specialist consultant in translating the concept into the practical work proposals and preparing the documentation for the Environment Agency. Also in our case, we needed the direction for the execution of the main practical work to be carried out.
INTERESTED PARTIES
It is imperative to ensure that all interested parties have been consulted and are supportive of the work planned: landowners or their representative, farmers, tenant farmers and land agents. This is best done between the advisory visit and the working out of the detailed plan of work to be presented to the Environment Agency. Notices should be displayed at site entrances to inform the public of the work before it starts.
NATURE OF THE WORK
River restoration work tends to fall into two broad categories; whether heavy plant
and a consultant are required as well as the volunteers, or work that can largely
be carried out by volunteers, working “in their own time”. Riffle and large woody
debris (LWD) work are the most dependent on the “expensive” deployment of heavy plant
and a consultant, and as the saying goes, “time means money”. The timing to bring
together these, and making ready the materials required and perhaps also the hire
of other equipment, has to be carefully co-
The RGCG in making the riffles required the consultant who also played a very active
part in the construction work, a tracked digger with operator, the hire of a dumper
truck driven by the consultant, and the in-
LWD also falls into the “heavy” plant and consultant category, but is simpler than the riffle work in that the trees can be cut and trimmed and kept out of the way but on site well before the time they are required. No dumper truck will be required, but a set of lifting chains are required. It is very useful, as in our case, if the digger driver also has a chain saw licence and can do felling, cutting and trimming of the trees, as well as moving them.
River narrowing, island creation and bank protection can all be done by hand labour. Preferably this is aided by some chain saw work for the coppicing of hazel (best), and the sectioning into stakes, batons and pegs, and for making up into faggots, while using the remaining brash as soft filling. The work can be carried out by one or more people, with some spread of timescale. It can be picked up and stopped again without undue detriment to the program of works, and can be fitted around more time and cost critical activities.
It is very useful to have a 4WD and trailer to take bulky and quite heavy woody materials to the positions where they are needed.
PLAN COMPLEXITY
Delays can be experienced, such as by a spell of wet weather, and in specific activities. The more complex the programme, and the level of interaction between activities, then the greater is the vulnerability to these and the chances of delays and the potential for something going wrong.
In our case we had planned two separate and parallel operations involving heavy plant work. The first was the RGCG work on riffles and LWD placements; the second the spoil bank removal being carried out by the Environment Agency team using a tracked digger and two dumper trucks. These could have operated quite separately, and any delay in one would not have affected the other.
However in this case we had embarked on a plan to recover stone and gravel from the spoil, and use this in the riffle work. This of course then linked the two operations through the production and supply of the stone and gravel.
Further the recovery of the stone and gravel introduced a third component into the
equation; a riddler/grader machine, a digger to feed the spoil to this, and an operator
to work both machines. To weigh against the value of the re-
There was in fact a 2-
In the final event, at the end of the first day of the Agency starting work by stripping
off much of the bank vegetation and spoil surface, it was clear that the yield of
stone and gravel would be low in relation to the need, and the riddling approach
was abandoned; and the two main exercises unhooked. Following this some 80-
The idea of recovery by riddling was good in principle, but even if the yield had lived up to expectation, in a tight timescale there was little room for any delay. The moral of this story is to look hard at dependent interactions in a plan. Here they carried with them both a degree of uncertainty (on yield of stone and gravel and the cost effectiveness), and a timing interaction (provision of material for other planned work). And perhaps there are much simpler ways in getting some of the benefits sought, in this case the picking up of larger flints material by hand from the spoil and barrowing it to where required.
KEY POINTS IN PLANNING A RIVER RESTORATION PROJECT